Under Pressure

Three years ago at a meeting at the Dargan Road premises, NIE highlighted that the local grid would be under pressure to support a large number of single wind generators. 

It was suggested that there may only be a possibility of connecting 200 medium sized wind turbines. Scant attention was given to this forewarning. At the time, Anaerobic Digesters and Solar PV arrays were not on the renewables agenda – they now are and so too is the reality that in many places, the 11kva grid and the 33kva infrastructure is now at saturation point.

“Conditional Offers” are now being furnished by the NIE generation team.  This “Gridlock” is now a major hurdle to the development of the Northern Ireland green economy.  NIE have made a proposal to the Utility Regulator to address this matter (see below).

These pressures continue to narrow the opportunities and the latest proposal is to reduce the threshold for obligated connections in line with England, Scotland and Wales.  In the case of a business where three phase is available, the current obligated threshold of 20kW will be reduced to 11kW and in the typical single phase set up, the 6.5kW threshold will be reduced to below 4kW.  These reductions could have a significant impact upon the viability of Solar PV and small wind projects.

LATEST (29th Oct 2013)KONICA MINOLTA DIGITAL CAMERA

33kV investment approval for Small Scale Generation
The GreenYard welcomes the investment approval by the Utility Regulator to NIE of up to £2.3m to facilitate additional small scale generation export from the 11kV network to the 33kV network.  According to NIE, this approval covers modest investments at 40 primary (33kV) substations, which will enable reverse power flow from the 11kV network to the upstream 33kV network when generation levels are high. Higher cost investments, which will require extensive 33kV capital works, are still under consideration by the Utility Regulator and NIE.

“While these investments will help maximise the remaining potential for small scale generation connections, it should be noted that the limited export capacity created in some areas will restrict the number of projects that can proceed.” [ref NIE website]

According to their website update, NIE is now developing a project plan and timelines for delivery of the approved 33kV investments. NIE will contact those applicants with conditional Connection Offers in areas where connection may now be possible in order to regularise their Connection Offers and progress their generation projects.  The GreenYard will continue to provide grid connection services to those seeking to apply for a G59 connection.