If you are thinking about installing a small Wind or PV on your premises, there are changes on the cards as regards how much generation capacity you can obtain without a grid application to NIE, i.e. plug in straight away to the grid under a G83 connection.
The current G83 limits are as follows:
- Single Phase – 6.5 kW
- Three Phase – 20 kW
The changes due to take effect on 1st March 2014 are:
- Single Phase – 3.68 kW
- Three Phase – 11.04 kW
Given the recent news regarding lack of generation capacity on the grid network this not surprising. However, it does mean that there is limited time left to connect a reasonable sized PV array or wind turbine without the need for applying for a G59 connection which can take over 3 months.
If you have been thinking about a renewable energy project we can provide independent PV panel and Wind Turbine comparisons and economic appraisals to help you get the most out of your project.
For more information on these changes visit the NIE website or contact us